Tool: Witness and Hold Points
27 D-B, 31 CM-GC
NCHRP Research Report 939 presents practical guidance for the post-award administration of projects delivered using alternative, nontraditional methods.
Tool: Witness and Hold Points (27 D-B, 31 CM-GC)
Session 8 of 8: December 1, 2022
What is it?
- A hold point is linked to an activity that should be inspected before the work becomes inaccessible
- A witness point is linked to a point in the work process where the agency may review, witness, inspect, or test any component, method, or process in the work
Why use it?
- Agency verifies work is proceeding per plan before it is covered or enclosed
How to use it?
- Establish witness and hold points before construction begins
- Agency and contractor work collaboratively to create inspection and testing procedures
- Hold points established where quality is critical
Documents
NCHRP ACM Contract Admin – Session 8 Slides